Embsay and Bolton Abbey Steam Railway

Embsay Junction to Embsay

The section of line between Embsay Junction and Embsay station is once more in use. This was the first stretch of line to be reopened in preservation as the track had been left in situ with the aim of serving Skipton Rock Company's quarry at Embsay. This never happened, and so the society was left with a short running line. The Junction is now roughly the site of Bow Bridge Loop.


(C) Charles Boylan
Slough Estates No. 5 is seen here in 1975 with a train composed of Altrincham Electric coaches approaching Embsay from Bow Bridge. At this time there was no Bow Bridge Loop, and the track was still doubled up to the junction. At the rear of the train is loco S100, which is now based on a different railway. This locomotive was identical to our own 140.
(c) Charles Boylan.
(C) YDRMT collection
Two locomotives that are no longer based at Embsay - Fred (Avonside, now in Belgium) and Chemicals (Barclay, now ???) - head for Bow Bridge from Embsay with one of the Altrincham Electric coaches.
(c) YDRMT collection.
(C) Jim Winkley
York No. 1 seen in a very similar location to the above photo, propelling the NER Director's Saloon (hence the green flag) back towards Embsay. The lifting of the second line is apparant here - it was used to extend the running line towards Skibeden Loop. The telegraph post in the background (left) marks the Grassington branch.
(c) Jim Winkley.
(C) Charles Boylan
This photograph from 1975 shows Joem's attempted steaming, between Embsay and Bow Bridge Loop. It is taken from the main road through Embsay, and clearly shows the large embankment upon which the railway is laid at this point. The locomotive at the rear is probably Primrose directly after arrival on the railway, and is approximately where Bow Bridge Loop is situated.
(c) Charles Boylan.
(C) Charles Adams
Fred and another loco (possibly S100?) between Embsay and Embsay Junction, showing the overgrown, but still intact, Down line.
(c) Charles Adams
(C) Charles Adams
Barclay 'Chemicals' (later sold back into industrial service at Crossley's Scrapyard, Shipley, where it was renamed 'Harry') with the Altrincham Electric coaches approaching Embsay station. The Down starter (which was originally slotted with Embsay Junction) is off, but the line itself has now been lifted to a certain extent.
(c) Charles Adams
(C) Charles Boylan
York No. 1 is seen here very close to Bow Bridge Loop, under a test having been vacuum fitted for hauling passenger trains. The down line has been removed, and was used in the first extensions towards Skibeden.
(c) Charles Boylan.
(C) Charles Adams
York No. 1 with the service train comprising the NER Directors' Saloon, a MkI suburban and the SR BY as brake. The start of Embsay village can be seen to the right. The signal post is presumably the Down starter, having been dug up, and is still in use today as the Down outer home (No.20 in Embsay Station signalbox).
(c) Charles Adams.
(C) Charles Adams
Bow Bridge Loop, very close to the site of the former Junction, plays host to Slough Estates No.5, just outshopped from its first overhaul on the Railway. The junction is located to the left of the picture, with Embsay Crag visible in the background.
(c) Charles Adams.
(C) Charles Adams
Another photo of Slough Estates at Bow Bridge, this time taken from close to where the former signalbox was located.
(c) Charles Adams.
(C) Charles Adams
Primrose with the passenger train having just entered Bow Bridge loop from Embsay. The line at this point is on an embankment, giving some good views of the trains from the road (to the left) as they run between Embsay and Bow Bridge.
(c) Charles Adams.
(C) Charles Boylan
Visiting well tank locomotive Bellerophon is seen here crossing Bridge 21 as it returns to Embsay Station in July 1988 when it visited the line in order to celebrate the Railway's centenary. Re-sleepering is underway in this photo. When it came to re-keying the line in 2000 / 2001, this bridge was found to be life expired and was subsequently replaced.
(c) Charles Boylan.
(C) YDRMT
Bridge 21 (the second bridge from Embsay Station towards Bow Bridge Loop) is a bridge over the stream, constructed as a skew bridge with wooden decking on metal girders which lie under where the rails are. However, the decking was found to be very rotten indeed, and these photos show the decking being removed. The first step was to remove the track, and this was achieved with a road-rail vehicle, loaned by GrantRail. Here it is seen posing, along with Mike Mason and Dave Barlow.
(c) YDRMT.
(C) YDRMT
This photograph looks back towards Embsay Station, and the rails have been removed by the road-rail vehicle. The decking where the second track lay has been cleared off inpreparation for the timber removal, and the rotten nature of the timbers can be seen. The rail wheels can be clearly identified on the road-railer, and the usefulness of these vehicles is apparant.
(c) YDRMT.
(C) William Lister
Scaffolding was errected underneath the bridge, and a decking was incorporated upon which the team could stand to remove the bridge decking. Here some timbers are being prepared to be lifted clear by the railway's diesel rail crane (as opposed to the steam crane) which was being used for the day.
(c) William Lister.
(C) William Lister
Looking towards Bow Bridge Loop the girders are apparant in this view of the bridge without its decking, so that their condition can be more thoroughly assessed.
(c) William Lister.
(C) Tim Warner
New girders were puchased for Bridge 21 and delivered to the Railway. At the same time, there was a rethink as to how the work would be carried out, with the result being that DRAB construction took the job on. The plan was to replace girders 1, 2, & 3 with new ones, insert a new girder in the centre of the formation, refurbish 1, 2 & 3 and use these to replace 6, 5 & 4 respectively. However, when these were removed it was decided NOT to try and refurbish them, but to acquire new girders when they are required.
(c) Tim Warner.
(C) Tim Warner
The old beams 1, 2 and 3 were craned out, allowing the new ones to be inserted, as can be seen here. The brickwork at the end of the beams still requires replacing in this picture, and the following one, owing to the difference between the new and old beams.
(c) Tim Warner.
(C) Tim Warner
Seen side-on, the new beams are undergoing painting in situ, prior to tie bars being fitted and handrails. The remaining old beams (4, 5 & 6) will be exchanged at a later date.
(c) Tim Warner.
(C) Tim Warner
The beams are seen in their final locations, painted and with the ties also fitted. This is looking towards Embsay station as the timber for the decking is installed.
(c) Tim Warner.
(C) Tim Warner
Looking the other way...
(c) Tim Warner.
(C) Tim Warner
Timber beginning to be laid for the new bridge decking whilst someone positions one of the original handrail supports in position prior to its attachment and painting.
(c) Tim Warner.
(C) Tim Warner
The line lies slumbering, waiting for the return of trains as the bridge nears completion. The first event held that made intensive use of the Bow Bridge section was the Harvest of Steam which saw the Sentinel, Ann hauling its first ever passenger trains. Event Photos.
(c) Tim Warner.
(c) Tim Warner
The first shuttle service to Bow Bridge each day only featured the Peckett, and therefore it had to run round its carriage before heading abck to Embsay. This provided variety, and also operational ease to get things in the right place. The embankment allows for easy viewing of the trains here, Embsay Junction being to the left, and Embsay Station to the right, with the Crag in the background.
(c) Tim Warner.
(c) Tim Warner
At Bow Bridge loop with Ann, the L&Y Directors' Saloon and visiting Peckett No.1438 from Scunthorpe.
(c) Tim Warner.
(c) Tim Warner
Upon arrival at Bow Bridge loop, No.22 runs round past the boxvans, ready to head along the full length of the line with the final goods train of the event.
(c) Tim Warner.


Top Photogalleries

Yorkshire Dales Railway Museum Trust (Holdings) Limited
Registered Charity No. 1116386
Bolton Abbey Station, Bolton Abbey, Skipton, North Yorkshire, BD23 6AF
General Enquiries: 01756 710614 - Talking Timetables & Fax: 01756 795189
enquiries AT embsayboltonabbeyrailway DOT org.uk webmaster AT embsayboltonabbeyrailway DOT org.uk
Yorkshire Tourist Board

Disclaimer - website (c) YDRMT 2009 -